CompTIA Project+ (PK0-005) — Question 252

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world. Which of the following should the project manager consider doing as part of the project planning?

Answer options

Correct answer: B

Explanation

Creating a handoff process (B) ensures smooth transitions and communication among team members in different locations, minimizing disruption. Monitoring the project team (A) and colocating the project team (C) may not be feasible for a global project, and creating a separate statement of work (D) does not directly address day-to-day performance issues.