CompTIA Project+ (PK0-005) — Question 251
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
Answer options
- A. Waterfall method
- B. Simulation method
- C. Precedence diagramming method
- D. Cost ratio analysis
Correct answer: C
Explanation
The Precedence diagramming method is the most suitable for constructing a project schedule and depicting dependencies, as it visually represents task sequences and relationships. The Waterfall method is a project management approach that does not focus specifically on scheduling or dependencies. The Simulation method is generally used for risk analysis rather than scheduling, and Cost ratio analysis pertains to financial assessments, not timeline creation.