Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

Answer options

Correct answer: B

Explanation

The best course of action is B, as it encourages the functional managers to follow the proper change management process, ensuring that any adjustments are formally documented and considered. Option A compromises project integrity, C risks informal changes without proper approval, and D dismisses the functional managers' concerns without seeking a resolution.