A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Answer options

Correct answer: C

Explanation

The correct answer is C because submitting a change request is a formal process that allows the project manager to seek approval for adjustments needed to address the project delays. Options A, B, D, and E are potential actions, but they do not follow the necessary protocol for managing scope changes in project management.