CompTIA Project+ (PK0-005) — Question 23
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
Answer options
- A. Update the work breakdown structure.
- B. Review the backlog.
- C. Seek baseline approval.
- D. Establish the resource pool.
Correct answer: C
Explanation
The correct answer is C, as seeking baseline approval is essential to ensure that all stakeholders agree on the project plan before moving forward. Options A and D are not the immediate next steps after defining tasks and costs, while B refers to a different aspect of project management that does not directly follow planning.