CompTIA Project+ (PK0-005) — Question 25

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

Answer options

Correct answer: C

Explanation

The correct answer is C, Customer notification, because it is essential to inform customers about the extended downtime to manage their expectations. Options A, B, and D do not directly address the issue of communication with customers regarding downtime and are therefore not relevant to the issue log in this context.