CompTIA Project+ (PK0-005) — Question 221

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Answer options

Correct answer: D

Explanation

The correct answer is D because reinforcing the rules of engagement ensures that all participants understand the boundaries and expectations for future meetings. Options A, B, and C do not directly address the immediate need to clarify participation guidelines, making them less appropriate in this situation.