CompTIA Project+ (PK0-005) — Question 222
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take NEXT?
Answer options
- A. Inform the CCB to stop communication.
- B. Establish a RACI matrix.
- C. Escalate the communication issues.
- D. Revise the communication plan.
Correct answer: D
Explanation
The correct answer is D because revising the communication plan can help streamline the flow of information and reduce unnecessary emails. Options A and C are not solutions to the problem, as stopping communication or escalating issues may exacerbate the situation. Option B, while useful, does not directly address the immediate concern of email overload.