CompTIA Project+ (PK0-005) — Question 220
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do NEXT?
Answer options
- A. Obtain details from the owner of the project.
- B. Update the critical path for the project.
- C. Apply contingency reserves.
- D. Reestimate epic user stories.
Correct answer: A
Explanation
The correct answer is A because obtaining details from the project owner is essential to understand the impact of the delays on the program. Updating the critical path (B), applying contingency reserves (C), or reestimating user stories (D) may be necessary later, but first, the program manager must gather more information to make informed decisions.