CompTIA Project+ (PK0-005) — Question 214

Project team members have questions regarding their responsibilities during the latest sprint. Which of the following personnel would MOST likely be able to assist?

Answer options

Correct answer: D

Explanation

The Scrum master is responsible for facilitating the Scrum process and helping team members understand their roles and responsibilities during a sprint. While the product owner, team leader, and product manager may provide guidance, it is the Scrum master who is specifically tasked with addressing questions related to the team's responsibilities within the sprint framework.