CompTIA Project+ (PK0-005) — Question 215

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update NEXT?

Answer options

Correct answer: C

Explanation

The correct answer is C, Issue log, because when a deliverable is rejected due to compliance issues, it becomes an identified issue that needs to be tracked and managed. The other options, such as Schedule, Status report, and Task board, do not directly address the need to record and monitor the compliance issue that has arisen.