CompTIA Project+ (PK0-005) — Question 213
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
Answer options
- A. The project manager did not release the resources.
- B. The project is in the verification testing phase.
- C. The project manager did not complete the project closure phase.
- D. The project manager did not remove access.
Correct answer: C
Explanation
The correct answer is C because if the project closure phase is not completed, the project remains open for ongoing tasks and responsibilities. Options A and D may also contribute to ongoing work, but they don't specifically address the completion of the project itself. Option B is incorrect as the project has already been released, indicating it is not still in the verification testing phase.