CompTIA Project+ (PK0-005) — Question 210
An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the MOST important prerequisites? (Choose two.)
Answer options
- A. Rollback plans
- B. Project management plan
- C. Deployment plan
- D. Asset management plan
- E. Communication plan
- F. Resource management plan
Correct answer: A, C
Explanation
Rollback plans are essential to revert changes if something goes wrong, ensuring system stability. A deployment plan is critical as it outlines the steps for implementing the change effectively. The other options, while important, do not directly address the immediate needs for safely executing and potentially reversing the change in a production environment.