CompTIA Project+ (PK0-005) — Question 209

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Answer options

Correct answer: D

Explanation

The correct answer is D, Email, because it allows the project manager to send information without knowing if the recipient will read it. In contrast, options A, B, and C involve direct communication methods that typically provide immediate feedback or acknowledgment from the recipient.