CompTIA Project+ (PK0-005) — Question 208
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?
Answer options
- A. Too much time might be spent generating project delays.
- B. The project manager might be seen as weak.
- C. The number of change requests throughout the project might be reduced.
- D. Some stakeholders might not be completely satisfied.
Correct answer: D
Explanation
The correct answer is D because when compromises are made, it is common for not all parties to feel fully content with the final solution. Option A is less likely since the goal of compromise is to avoid significant delays. Option B is incorrect because being a facilitator of compromise does not inherently indicate weakness. Option C is also not a guarantee, as change requests can still arise even with initial compromises.