CompTIA Project+ (PK0-005) — Question 207
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following would most likely take place during a Scrum ceremony?
Answer options
- A. Reviewing project blockers
- B. Defining roles and responsibilities
- C. Establishing a project schedule
- D. Determining a project budget
Correct answer: A
Explanation
During a Scrum ceremony, particularly in events like the Daily Scrum, reviewing project blockers is essential for the team to identify and address any obstacles to progress. The other options, such as defining roles, establishing schedules, and determining budgets, are not typically part of Scrum ceremonies, as they focus more on team collaboration and iterative progress.