CompTIA Project+ (PK0-005) — Question 203
After returning from a vacation, a project manager learns the company’s new administration released a memo communicating plans to reduce costs in projects. Which of the following should the project manager do first?
Answer options
- A. Transfer the projects to an external consulting firm to prevent their failure.
- B. Wait for the new administration to express opinions about the projects.
- C. Resign and leave the projects, as there will be no chance to finish them.
- D. Present the projects that are underway and describe their relevance to the organization.
Correct answer: D
Explanation
The correct answer is D because presenting the projects and their significance helps demonstrate their value to the organization, which may influence decision-makers. Options A and C are drastic measures that do not address the situation proactively, while option B lacks initiative and does not contribute to addressing the cost reduction plans effectively.