A project manager has decided to make a scope change in the SOW. Which of the following should the project manager do first in the process?
Answer options
- A. Discuss with a team lead.
- B. Move to the next step in the process.
- C. Communicate with the project sponsor.
- D. Have a meeting with the human resources department.
Correct answer: C
Explanation
The project manager should first communicate with the project sponsor because they have a vested interest in scope changes and need to be informed and possibly approve the alterations. Discussing with a team lead or moving to the next step without the sponsor's input would be premature, and meeting with HR is irrelevant to the scope change process.