CompTIA Project+ (PK0-005) — Question 202

A project manager has decided to make a scope change in the SOW. Which of the following should the project manager do first in the process?

Answer options

Correct answer: C

Explanation

The project manager should first communicate with the project sponsor because they have a vested interest in scope changes and need to be informed and possibly approve the alterations. Discussing with a team lead or moving to the next step without the sponsor's input would be premature, and meeting with HR is irrelevant to the scope change process.