CompTIA Project+ (PK0-005) — Question 205
A project team wants to compare two potential vendors’ costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
Answer options
- A. Scatter diagram
- B. Decision tree
- C. Pareto chart
- D. Histogram
Correct answer: B
Explanation
A decision tree is the most appropriate choice as it allows the team to visualize different decision paths, including costs and associated risks for each vendor. The other options, such as a scatter diagram and histogram, do not effectively represent the decision-making process involving multiple factors, while a Pareto chart focuses on identifying the most significant factors rather than comparing vendors.