CompTIA Project+ (PK0-005) — Question 20
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP. Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
Answer options
- A. Milestone chart
- B. Work breakdown structure
- C. Project charter
- D. Detailed scope statement
Correct answer: C
Explanation
The correct answer is the Project charter, as it serves as the initial document that outlines the project's objectives and boundaries, helping to align stakeholder expectations. While the other options like the Milestone chart and Work breakdown structure are important, they come into play after the project's charter has been established to define the scope in more detail.