CompTIA Project+ (PK0-005) — Question 18

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Answer options

Correct answer: A

Explanation

The Issue log is the most suitable tool for documenting the impacts of the delay caused by the hurricane, as it specifically tracks problems and their effects on the project. A Gantt chart and Milestone chart are used for scheduling and tracking progress, but they do not capture the details of issues. The Change control log is used for managing changes in project scope, not for documenting delays or their consequences.