A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?
Answer options
- A. Forcing
- B. Avoiding
- C. Compromising
- D. Smoothing
Correct answer: B
Explanation
The project manager is using the avoiding technique because they are not addressing the issues that arose during the meeting and are choosing to ignore the need for a standardized process. Forcing involves imposing a solution, compromising seeks a middle ground, and smoothing focuses on maintaining relationships, none of which reflect the project manager's decision to move forward without changes.