CompTIA Project+ (PK0-005) — Question 179

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement. Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

Answer options

Correct answer: C

Explanation

The Traceability matrix is the best tool for ensuring that each requirement is linked to its corresponding deliverable, allowing stakeholders to see how requirements are being met. The Risk register tracks potential project risks, the Change log documents modifications made, and the Project status report provides an overview of project progress but lacks specific details on requirement coverage.