CompTIA Project+ (PK0-005) — Question 177
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Choose two.)
Answer options
- A. Purchase the materials.
- B. Assign the resources.
- C. Accept delays in the work.
- D. Approve the deliverables.
- E. Monitor the performance.
- F. Negotiate with the vendors.
Correct answer: E, F
Explanation
The project manager should monitor the performance to ensure the work is progressing as planned and negotiate with the vendors to address any issues or changes that may arise. Other options, like purchasing materials or accepting delays, do not align with the proactive role needed in managing outsourced work.