CompTIA Project+ (PK0-005) — Question 174

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the following has the project manager identified?

Answer options

Correct answer: C

Explanation

The correct answer is C, as language barriers can lead to miscommunication and misunderstandings regarding project requirements. The other options, while relevant in different contexts, do not specifically address the issue of misinterpretation caused by communication difficulties.