CompTIA Project+ (PK0-005) — Question 173

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Answer options

Correct answer: D

Explanation

Scrum is an agile methodology that emphasizes iterative progress and frequent delivery of functional components, making it ideal for accommodating stakeholder requirements for multiple milestones. In contrast, Waterfall is a linear approach that lacks flexibility, SDLC is a broader framework that does not specifically focus on iterative delivery, and XP, while agile, is more focused on technical practices than on stakeholder engagement.