A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

Answer options

Correct answer: A

Explanation

The Agile methodology is ideal for projects where requirements may evolve, allowing for flexibility and iterative development. In contrast, SDLC, Waterfall, and PRINCE2 are more structured and may not accommodate changing requirements as effectively, making them less suitable for this scenario.