During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
Answer options
- A. Status report
- B. Issue log
- C. Risk report
- D. Risk register
Correct answer: C
Explanation
The correct answer is C, the Risk report, as it specifically addresses potential risks that could impact the project's success. The other options, such as the Status report and Issue log, do not focus primarily on risks, while the Risk register is more of a repository than a communication tool.