CompTIA Project+ (PK0-005) — Question 159

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date. Which of the following tools should the project manager use first to update the findings?

Answer options

Correct answer: A

Explanation

The correct answer is A, the Defect log, as it is specifically designed to track bugs and defects found during testing. The Change log records changes to project scope, the Issue log captures general project issues, and the Risk log is for potential risks, making them less relevant for documenting bugs.