CompTIA Project+ (PK0-005) — Question 158

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

Answer options

Correct answer: A

Explanation

The correct answer is 'Exploit' because Project A is taking advantage of the work done by Project B to enhance its own progress. The other options do not apply here: 'Share' involves collaboration on risks, 'Transfer' means shifting the risk to another party, and 'Accept' refers to acknowledging the risk without action.