CompTIA Project+ (PK0-005) — Question 156

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete next?

Answer options

Correct answer: D

Explanation

The correct answer is D because after updating the project plan, the next step is to implement the approved change. Options A, B, and C involve preliminary steps or analyses that should have been completed before deciding to enact the change.