CompTIA Project+ (PK0-005) — Question 155

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers
• High uncertainty about existing systems
• Risk of frequent requirement changes
• Tight deadlines

Which of the following project methodologies would be BEST to use in this situation?

Answer options

Correct answer: D

Explanation

The correct answer is D, XP (Extreme Programming), as it is designed to handle frequent changes and high uncertainty, making it ideal for projects with tight deadlines and a limited number of developers. PRINCE2 (A) is more rigid and structured, Scrum (B) may not fully address the extreme level of requirement changes, and SAFe (C) is more suited for larger teams and projects, making them less appropriate for this specific situation.