CompTIA Project+ (PK0-005) — Question 154
Following the approval of a change by the CCB, which of the following should a project manager consider NEXT when deploying a new networking device into an existing production environment?
Answer options
- A. Maintenance window
- B. Risk assessment
- C. Operational security
- D. Validation check
Correct answer: A
Explanation
The correct answer is A, as establishing a maintenance window is crucial for minimizing disruptions during the deployment of new devices. While risk assessment, operational security, and validation checks are important, they should ideally be conducted before or concurrently with planning the maintenance window, not after change approval.