CompTIA Project+ (PK0-005) — Question 153

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which of following techniques is the project manager utilizing?

Answer options

Correct answer: C

Explanation

The correct answer is C, as an interview involves direct interaction where stakeholders can share their insights. While brainstorming (B) encourages creative idea generation, it is more structured and typically involves a group. Process modeling (A) focuses on visualizing processes, and a focus group (D) is a structured discussion rather than a one-on-one interview.