CompTIA Project+ (PK0-005) — Question 160

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the MOST important for the team to take into consideration?

Answer options

Correct answer: B

Explanation

The most critical factor is the 'Impact to project' since it helps prioritize tasks that will deliver the most value to the project. While 'Time to be fixed,' 'Issue category,' and 'Resource availability' are important, they do not directly influence the overall benefit to the project as effectively as the impact does.