CompTIA Project+ (PK0-005) — Question 146

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following BEST describes what the team is developing?

Answer options

Correct answer: D

Explanation

The correct answer is D, a transition plan, as it encompasses the necessary elements for moving operations from project completion to ongoing management. The other options, such as the project closeout report and phase-gate review documentation, focus on different stages of the project lifecycle and do not specifically address the operational handoff and training aspects.