CompTIA Project+ (PK0-005) — Question 146
A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following BEST describes what the team is developing?
Answer options
- A. The project closeout report
- B. A handover to operations
- C. Phase-gate review documentation
- D. A transition plan
Correct answer: D
Explanation
The correct answer is D, a transition plan, as it encompasses the necessary elements for moving operations from project completion to ongoing management. The other options, such as the project closeout report and phase-gate review documentation, focus on different stages of the project lifecycle and do not specifically address the operational handoff and training aspects.