CompTIA Project+ (PK0-005) — Question 145

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Choose two.)

Answer options

Correct answer: E, F

Explanation

The correct answers, E and F, pertain to validating the deliverables and reconciling the project budget, which are essential tasks during project closure. The other options, such as creating a backlog, managing quality, updating issue logs, and performing risk assessments, are more relevant to other phases of the project lifecycle rather than closure.