CompTIA Project+ (PK0-005) — Question 147
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:
Answer options
- A. the preferred sponsor's communication channel.
- B. the preferred project manager's communication channel.
- C. the preferred reported communication channel.
- D. email communication as the preferred communication channel.
Correct answer: C
Explanation
The correct answer is C because the stakeholder register should reflect the communication preferences reported by the stakeholders. Option A and B focus on individual roles rather than the collective preference, while D specifies only one option instead of the preferred reported channel.