CompTIA Project+ (PK0-005) — Question 141
A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?
Answer options
- A. Gantt chart
- B. Project organization chart
- C. Program Evaluation Review Technique chart
- D. Milestone chart
Correct answer: D
Explanation
The Milestone chart (D) is the best tool for tracking high-level progress in a project by focusing on significant events or achievements. In contrast, a Gantt chart (A) provides detailed scheduling, a Project organization chart (B) outlines team structure, and a Program Evaluation Review Technique chart (C) is more suited for assessing project risks and timelines rather than providing high-level updates.