CompTIA Project+ (PK0-005) — Question 142
Several stakeholders have declined the invitation for the kickoff of a major digital transformation project. Which of the following actions should the project manager take NEXT?
Answer options
- A. Escalate directly to the project sponsor.
- B. Push the kickoff meeting out by one week.
- C. Proceed with the kickoff as planned.
- D. Identify replacements for project stakeholders.
Correct answer: A
Explanation
The correct action is to escalate directly to the project sponsor, as they can help address the issue of stakeholder absence and ensure their involvement. Pushing the meeting out or proceeding without key stakeholders may lead to a lack of support and commitment, while identifying replacements may not be feasible in the short term.