CompTIA Project+ (PK0-005) — Question 140
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform FIRST?
Answer options
- A. Define the WBS.
- B. Develop a RAM.
- C. Manage the vendors.
- D. Assess the resource pool.
Correct answer: B
Explanation
Creating a Responsibility Assignment Matrix (RAM) is crucial as it outlines roles and responsibilities, ensuring that access requirements are identified early on. Defining the WBS, managing vendors, and assessing the resource pool are important but come after establishing the RAM for clarity on access needs.