During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member MOST likely consulting?

Answer options

Correct answer: C

Explanation

The correct answer is C, the Burndown chart, as it specifically tracks the amount of work remaining over time, helping teams visualize progress towards completion. The other options, while useful for project management, do not focus on tracking work remaining in an agile context. The Pareto chart is for identifying major issues, the Milestone chart outlines key project dates, and the Gantt chart shows task timelines but not specifically work left to do.