CompTIA Project+ (PK0-004) — Question 95
A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation.
Which of the following actions has the PM omitted?
Answer options
- A. Identifying the risk
- B. Obtaining approval from the CCB
- C. Evaluating the impact of the risk
- D. Communicating to stakeholders
Correct answer: B
Explanation
The correct answer is B because the PM should have sought approval from the Change Control Board (CCB) before submitting the change request. Options A, C, and D are important steps, but they do not directly relate to the approval process that is essential in change management.