A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation.
Which of the following actions has the PM omitted?

Answer options

Correct answer: B

Explanation

The correct answer is B because the PM should have sought approval from the Change Control Board (CCB) before submitting the change request. Options A, C, and D are important steps, but they do not directly relate to the approval process that is essential in change management.