CompTIA Project+ (PK0-004) — Question 96
A PM has a complex project that requires coordination among numerous stakeholders. Which of the following is the MOST appropriate type of meeting for the stakeholders to hold?
Answer options
- A. Virtual
- B. Impromptu
- C. One-on-one
- D. In-person
Correct answer: A
Explanation
A Virtual meeting is the best choice for coordinating among many stakeholders as it allows participants from different locations to join easily. Impromptu meetings may lack structure, while One-on-one meetings do not facilitate group discussions, and In-person meetings can be challenging to organize with numerous stakeholders.