CompTIA Project+ (PK0-004) — Question 94
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance.
Which of the following should the PM do NEXT?
Answer options
- A. Crash the schedule.
- B. Notify the project team.
- C. Initiate a change request.
- D. Accept the risk.
Correct answer: B
Explanation
The next step for the project manager is to notify the project team about the change in schedule and defect tolerance, ensuring everyone is aligned with the new expectations. Crashing the schedule, initiating a change request, or accepting the risk may be considered later, but informing the team is crucial to moving forward effectively.