A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to escalate the issue. Which of the following documents should the project manager consult?
Answer options
- A. Issue log
- B. RACI chart
- C. Risk management plan
- D. Organizational chart
Correct answer: B
Explanation
The correct answer is B, the RACI chart, as it outlines the roles and responsibilities of team members, helping the project manager understand who to escalate issues to. The Issue log (A) records problems but does not guide escalation; the Risk management plan (C) focuses on potential risks rather than team dynamics; and the Organizational chart (D) shows the hierarchy but lacks detail on responsibilities.