CompTIA Project+ (PK0-004) — Question 92

During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances.
The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?

Answer options

Correct answer: A

Explanation

The correct answer, A, indicates that the complaints are due to a decrease in deliverable quality, likely stemming from the use of cheaper materials. Option B is incorrect because the PM did communicate with the sponsor. Option C implies quality assurance wasn't updated, but that doesn't directly address stakeholder complaints. Option D is also incorrect as the change was approved by the sponsor.