CompTIA Project+ (PK0-004) — Question 69
A project has a ׀’׀׀¡ of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do
NEXT?
Answer options
- A. Add the required work to complete the project behind $892,500.
- B. Evaluate the impact and justify adding new work to the project.
- C. Obtain approval from the CCB.
- D. Request a budget increase of $170,000.
Correct answer: C
Explanation
The correct answer is C because obtaining approval from the CCB is essential for any changes to the project scope or budget. Options A and D do not follow the proper channels for managing project changes, and B, while a good step, does not address the immediate need for formal approval.