CompTIA Project+ (PK0-004) — Question 66
An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?
Answer options
- A. PMO
- B. Project sponsor
- C. Project coordinator
- D. HR
Correct answer: B
Explanation
The Project sponsor is the individual who provides guidance and support for the project, ensuring that resources are allocated effectively. The PMO typically oversees project management standards but does not directly manage resources. The Project coordinator assists with project tasks but does not have the authority to allocate resources, and HR focuses on personnel management rather than project-specific resource allocation.