CompTIA Project+ (PK0-004) — Question 65
A PM is reviewing bids from vendors and has a question.
Which of the following documents should the PM use to obtain a response?
Answer options
- A. Project schedule
- B. RFP
- C. Quotation
- D. RFI
Correct answer: B
Explanation
The correct answer is B, the RFP (Request for Proposal), as it is specifically designed to solicit detailed responses from vendors regarding their bids. The other options, such as Project schedule, Quotation, and RFI (Request for Information), do not serve the primary purpose of obtaining detailed responses to proposals.